WEST SIDE:
Queen to Superior – boulevard preparation is ongoing for remaining paving stones. The work is expected to begin within mid August.
Superior to Clandeboye – sidewalk prep continues, concrete pouring is scheduled for the first week of August.
Clandeboye to Eaton – demolition and excavation continues, silva cell installations will be completed by the August long weekend.
Please be advised: The first week of August will see a lot of concrete work in various portions of the project. With concrete work comes an influx of workers so please proceed through project area with caution and expect periods of delay.