Vaughan Avenue – Packer was onsite today. Asphalt work to begin tomorrow (July 26th)
Manchester Avenue – Asphalt approaches completed.
Mercy Avenue – Asphalt approaches completed.
Morris Avenue – Work ongoing.
Dufferin Avenue – Prep work being done today. Asphalt overlay scheduled for July 27th.