Watermain North to the Wastewater Treatment Plant
The watermain installation on Main Street from Lake Avenue to the Wastewater Treatment Plant is completed.
The watermain installation on Main Street from Lake Avenue to the Wastewater Treatment Plant is completed.
Wastewater sewers and land drainage sewers have been installed. The City has been advised that there is a delay in having the watermain liner installed and this work is expected…
Maple Leaf Construction started on curb and gutter work and sidewalk preparation on June 17th. We anticipate that asphalt work will be completed by the end of next week.
More than $2.75 million will be invested into improvements to Selkirk’s Main Street this summer, with work beginning this week. An open house will be held in Selkirk Council Chambers…