Manitoba Avenue East Revitalization – the north parking lot is now open for public parking. The contractor is done with the lane closures on Manitoba Avenue, but will be continuing with tree and shrub planting today and into next week. The parking lot beside the Selkirk Record will be closed on Monday and Tuesday to the public while the contractor is working in that area.
Manchester Avenue Wastewater and Land Drainage Sewer – work is completed.
Manchester Watermain Liner – work starting on Monday, June 8th.
Main Street Watermain Renewal – work is completed except for boulevard restoration.