Update: August 10, 2022
Eveline Street Reconstruction: framing on the interior of the round about is ongoing with curb pouring continuing tomorrow and Friday. Concrete sidewalk, curb framing and pouring tie-ins ongoing between Eaton…
Eveline Street Reconstruction: framing on the interior of the round about is ongoing with curb pouring continuing tomorrow and Friday. Concrete sidewalk, curb framing and pouring tie-ins ongoing between Eaton…
UPDATE: The Public Hearing was completed; please see Council Meeting Minutes for the decision and outcome.
Eveline Street Reconstruction: gravel base work still being done on the round about on Eveline by Selkirk Park entrance. On the west side of the street between Clandeboye and Eaton,…
Eveline Street Reconstruction: on the west side of Eveline, gravel base work is ongoing on the round about. Boulevard prep is ongoing between Dufferin and Superior with concrete pouring beginning…
UPDATE: The Public Hearing was completed; please see Council Meeting Minutes for the decision and outcome.