Toronto Avenue Watermain Renewal – land drainage work is ongoing and will continue for approximately another two weeks. Please be mindful of equipment in the area.
Main Street Reconstruction – sidewalk construction has begun on both the east side and west side of Main Street between Manitoba Avenue and Morris Avenue and will continue for another couple of weeks. Land drainage work on Morris Avenue is ongoing and is anticipated to last another week or so. The force main installation project is still probably a month away, however, select property owners on Main Street will be receiving notices of driveway access limitations for Thursday, June 27th. The bike path portion of the project has not started yet.