Update: July 19, 2024
Toronto Avenue Land Drainage Sewer Install: work on the new land drainage sewer pipe is about halfway completed. It is anticipated that this portion of the Toronto Avenue projects will…
Toronto Avenue Land Drainage Sewer Install: work on the new land drainage sewer pipe is about halfway completed. It is anticipated that this portion of the Toronto Avenue projects will…
Active Transportation Pathway from Eveline to Waterfront – landscaping ongoing. Multi-use Pathway Installation in Selkirk Park between Entrance and Campground Office – landscaping ongoing. Watermain Renewal on 300 and 400…
Active Transportation Pathway From Eveline to Waterfront: the City-owned parking lot just south of Superior Avenue on Eveline Street will be closed starting today until Thursday, June 8th while work…
Sutherland Avenue Watermain Renewal: starting tomorrow (Tuesday, May 30th) there will be no parking on the 300 and 400 blocks of Sutherland Avenue as well as 50m west of the…
Sutherland Avenue Watermain Renewal: contractors are on Sutherland Avenue getting connections ready for the watermain renewal. There could be intermittent traffic disruptions next week but residents should still be able…