Update: July 21, 2022
Eveline Street Reconstruction: construction work on the west side of Eveline between Eaton and Queen continues. The contractor is continuing with concrete work, brick work and installing silva cells. Excavation…
Post Type to identify and post infrastructure projects in the City of Selkirk.
Eveline Street Reconstruction: construction work on the west side of Eveline between Eaton and Queen continues. The contractor is continuing with concrete work, brick work and installing silva cells. Excavation…
Eveline Street Reconstruction: Starting tomorrow and continuing throughout the week, the contractor will be excavating the rest of the west side boulevard & sidewalk from Eaton to Superior. Sidewalk and…
Eveline Street Reconstruction: With the start of the Fair & Rodeo weekend, only some minor work will be done on Eveline Street and no heavy equipment will be running.
Eveline Street Reconstruction – boulevard work on both the east and west sides of Eveline Street ongoing. Concrete sidewalks will continue to be poured on the west side from Superior…
Eveline Street Reconstruction: Roundabout excavation and construction continues on the west side boulevard of Eveline Street from Queen to Dufferin. Queen to Dufferin east side excavation and construction continues. Sidewalks…