Update July 31, 2020:
Manchester Avenue – with the majority of top soil now completed, the landscapers will be onsite next week Tuesday and Wednesday (August 4th and 5th) to lay sod. The lane…
Post Type to identify and post infrastructure projects in the City of Selkirk.
Manchester Avenue – with the majority of top soil now completed, the landscapers will be onsite next week Tuesday and Wednesday (August 4th and 5th) to lay sod. The lane…
Manchester Avenue — Due to the extreme heat this last week, the City has decided to hold off on finishing the landscaping on Manchester Ave. until after the weekend. We…
Manchester Avenue Roadwork – contractor will start framing and pouring concrete sidewalks tomorrow (Wednesday, July 1st). Main Street Watermain Renewal – contractor will start framing and pouring concrete sidewalks tomorrow…
Manchester Avenue Roadwork – curb and gutter work will start tomorrow (Thursday, June 25th). There will be no road access on Thursday, or access to driveways on Thursday, June 25th…
Manchester Avenue – wastewater sewer and land drainage sewer work completed. Watermain liner work completed. The contractor will be here on Monday, June 15th to start on the road works.…